Vale Verde and Appian report first blast at Serrote
Mineração Vale Verde and Appian Capital Advisory announced on Tuesday the first blast at the Serrote copper-gold project in Alagoas, Brazil.
According to Appian, the pre-stripping program has now handled over one million tonnes of material. Construction and engineering works are progressing to plan, with start-up expected in H2 2021.
Based on definitive feasibility study (“DFS”), Serrote will require $250 million in capital for a conventional, low-strip open-pit operation targeted to produce 20,000 tonnes of copper equivalent per year over 14 years.
“Serrote continues to demonstrate robust economics with potential upside, and we are seeing strong interest from offtake and financing partners,” said Paulo Castellari, CEO, Vale Verde & Appian Brazil.
More News
GRAPH: Cobalt price plunge and the EV market
February 11, 2025 | 04:03 pm
China funnelled $57 billion to control critical mineral supply chain
February 05, 2025 | 11:00 am
{{ commodity.name }}
{{ post.title }}
{{ post.date }}
Comments